Cost of jail report soars to $1.16 million

 

05/25/2006

By William J. Kemble , Correspondent

Daily Freeman Artcile

www.dailyfreeman.com

 

Cost of jail report soars to $1.16 million

KINGSTON - A report commissioned by Ulster County in June 2004 to document what went wrong in the planning and construction of the county Law Enforcement Center has ballooned in cost from the originally approved $150,000 to $1.16 million.

The full 46-page report by consultant Hill International has been withheld from the public under the justification that it will be used in future litigation over construction delays and cost overruns. But about 6,000 pages in documentation intended to bolster the report were released by the county following a Freedom of Information Law request by the Freeman. Those pages appear to consist entirely of daily construction reports printed directly from a Web site operated by construction manager Bovis Lend Lease.

In other words, Ulster County taxpayers first paid Bovis Lend Lease to create the 6,000 pages of written records, then paid again to have Hill International copy those records, which were presented as the underpinning of the 46-page report.

A senior county official says the body of work produced by Hill International for the $1.16 million consists entirely of the 46-page report and the 6,000 pages of copied documents.

Hill International officials deny their fees skyrocketed from $150,000 to $1.16 million largely for the copying of material from the Web site, but they decline to explain the cost run-up.

Hill Senior Vice President Frank J. Giunta said it was unfair to characterize the body of work as being produced under the resolution that authorized payment of only $150,000, but he declined to elaborate.

"I can tell you, on the record, that (the resolution's) fee arrangement is not correct," he said. "The real fee arrangement is a matter that is more appropriately discussed between us and our client."

The $1.16 million in payments apparently included time spent by Hill International in developing the 46-page report, which was presented to Ulster County legislators behind closed doors on April 25. But County Attorney Joshua Koplovitz said a detailed explanation of the costs has not been provided during the four months he has been in office.

"I don't know how much time they spent conducting their analysis," he said. "That (46-page presentation and the Bovis Lend Lease reports) is the entirety of the papers that have been generated."

Richard Parete, chairman of the county Legislature's Law Enforcement Center Project Committee, has been critical of Hill International recommendations that he says would keep that company as a consultant to the county with steep fees and little effort involved. He said his suspicions about Hill's performance were supported by the firm's presentation to the county of supporting papers that merely were copies obtained from another company's Web site.

"That's all Bovis' documents," said Parete, D-Accord.

"I think that's a waste of taxpayer money," he said. "It's an embarrassment."

County officials have released about half of a computer presentation of the 46-page report given by Hill International during a special county meeting April 25. The county was billed $3,500 for that presentation alone, which followed 22 months of work by Hill.

And though the presentation was scheduled to be given in the Legislature's chamber, the 33 county lawmakers were forced into a corner conference room when the company's laptop computer failed.

Legislature Chairman David Donaldson said it was not clear why the background material for the presentation was printed directly from Bovis Lend Lease's Web site.

"What they advised us is the information they used was from the contractors themselves," Donaldson said, adding that lawmakers were told by Hill that the company it "did not use information from Bovis to make their determination."

Donaldson, D-Kingston, blamed Republicans - who controlled the county Legislature until the end of 2005 - for allowing the problems that have caused the Law Enforcement Center's cost to balloon from an original estimate of $53 million to more than $86 million, with the final cost predicted to top $100 million. The project also is more than two years behind schedule and still has no target completion date.

"We inherited this mess, and we're trying to clean it up," he said.

County officials have intended to use the Hill International report to settle claims filed with the county by contractors who are seeking money related to the project's delays.

Among the amounts being sought:

* $722,499 by Eastern Heating & Cooling for temperature controls.

* $4.79 million by Rotondo Weirich for precast cells.

* $2.57 million by C.B. Strain & Sons for mechanical, heating, ventilation and air conditioning work.

* $158,069 by S&S Fire Suppression for sprinkler installations.

* $113,479 by STS Steel for structural steel.

* $25,745 by Reallife Landscaping for grounds work.

Koplovitz said the county is considering suing some of the contractors based on the 25 pages being withheld from the public from Hill's 46-page report.

Hill International, a contractor hired under the original bidding for the project, had its first budget line set at $250,000 to be a consultant for the review of administrative expenses, an expenditure justified by the county as "legal fees" for "sheriff's expenses." A county payment sheet shows the firm had been paid $333,118.47 on that budget line as of April 25.

A second budget line for Hill was established on June 10, 2004, through a county Legislature resolution approving $150,000 for "claims review and management," which was intended to provide legislators with recommendations for cost savings on the project and provide technical assistance to the county's legal counsel for the project. But that budget line has been increased to $1.16 million, of which $1.06 million has been paid to date to Hill International.

After the public availability of the 6,000 pages in background documents was announced on April 26, the information was delayed until May 8 while the Bovis Lend Lease log was bound in three-ring binders.

Information in the log includes the daily weather conditions, names of contractors at the job site on Albert Street in Kingston and special notes about problems found at the site. These begin with an Oct. 11, 2002, entry written by Bovis Lend Lease Site Manager Mike Martin, who reported on a page marked "First Day" that it was 55 degrees upon arrival at 6:45 a.m. and 69 degrees at 4 p.m.

The entry further notes: "Perralla trailer #1 and #2 delivered and setting up. 2 men first day of mobilization."

In a preliminary review of items from the log, called "Daily Details" by the Bovis Lend Lease Web site, there were issues of control over the site addressed in a Nov. 2, 2002, entry stating concern when a carpenters' union representative came to the Albert Street property.

"Asked rep to announce that we do not want soliciting on job site and that visitors must sign at the Bovis field office," Martin wrote.

Routine problems at the site also are in the journals, with a major safety issue appearing in a Feb. 19, 2003, entry stating that David Christa Construction has "third unprotected rebar (steel reinforcement bar) violation. Next violation, fines of $100 will be levied on each unprotected bar."

On Feb 20, 2003, the log reports that "Bovis made a inspection of site at end of day - all rebar was covered."

As the project proceeded, the Bovis Lend Lease log shows a steady list of safety issues with individual contractors was addressed through David Christa Construction. Among the earliest extended lists was one on June 30, 2003, with an entry noting: "Rebar being cleaned up slowly - tripping hazard, many rebar caps missing/removed, poor safety around elevator foundation in area D, told mason to add protection to scaffold over ramp at back of E area (6/26/03), received complaints regarding water on floor in area F poses a safety hazard."

The Law Enforcement Center, when complete, will house the county's jail and sheriff's office. The jail currently is on Golden Hill Drive in Kingston, not far from the new facility. The sheriff's office is in a rented building on Schwenk Drive in Kingston.